158kV 250MVA Power Transformer – High-Voltage Substation Autotransformer
- Primary Voltage Ratings 132kV, 138kV, 158kV or others
- Secondary Voltage Ratings 32.4/13.8/11/10.5/6.6/6.3kV or customized
- H.V. Tap Range ± 8×2.5% HV taps or others
- Type Oil-immersed power transformer
- BIL up to 350kV
- Standards IEEE, ANSI, IEC
- Application grid interconnection points, regional power hubs, and backbone utility networks
- Power Rating 250MVA
- Certificate UL, CESI, ISO, KEMA
- Cooling Method ONAN/ ONAF
- Opeartion Step Down & Step Up
Technical Specifications
| Rated Power | 250MVA |
| Rating Primary Voltage | 132kV, 138kV, 158kV |
| Secondary Voltage |
32.4/13.8/11/10.5/6.6/6.3 kV Customized |
| Frequency | 50/60Hz |
| Vector Group | Dyn11, YD11, YNd11 |
| Winding Material | Aluminum/Copper |
| Efficiency | As IEEE, CAS Std or Customized |
| Impedance Voltage | As IEC |
| Altitude | ≤1,000m or Customized |
| Enclosure material | Mid Steel |
| HV Bushing |
| LV Bushing |
| OLTC/NLTC |
| Lifting hook for complete transformer |
| Name plate |
| Oil temperature |
| Winding temperature |
| Radiators |
| Oil level |
| Pressure relief valve |
| CT |
Customization Optional
Packing and Shipping
The autotransformer main body is mounted on a heavy-duty transport frame engineered to distribute weight evenly and minimize mechanical stress. Stabilizing supports, shock-absorbing materials, and reinforced bracing are applied at critical structural points to reduce vibration and impact during transit. Protective wrapping systems, combined with desiccants and moisture barriers, are used to maintain insulation integrity. For long-distance or overseas shipments, additional preservation measures such as inert gas filling or controlled vacuum sealing may be applied.
Transportation methods are selected based on transformer dimensions, route conditions, and logistical constraints. Depending on project requirements, shipment may be arranged using flat-rack containers, open-top containers, or break-bulk cargo. All packing materials comply with international export regulations, including ISPM-15 standards for wooden components. Clear markings identify lifting points, center of gravity, orientation limits, and safety instructions to ensure correct handling during loading, unloading, and site transfer.
Each shipment includes a complete documentation package containing packing lists, inspection records, quality certificates, test reports, technical drawings, and operation manuals. Upon arrival at the site, customers receive detailed instructions for unloading, storage, and installation. Optional on-site services such as technical supervision, oil processing, component installation, and commissioning support are available to ensure safe installation and reliable commissioning.
Manufacturer Test
Progress test
Progress testing for the 158kV 250MVA High-Voltage Substation Autotransformer is conducted as a structured quality control program throughout manufacturing. Incoming materials, including magnetic steel, conductors, insulation components, and insulating oil, are inspected for compliance with approved specifications. During core assembly and winding fabrication, inspections verify dimensional accuracy, mechanical stability, and insulation placement. The active assembly undergoes controlled drying and vacuum processing, with continuous monitoring of temperature and moisture parameters.
Intermediate checks include electrical continuity verification, winding resistance measurement, and preliminary ratio confirmation prior to final assembly. Tank fabrication is inspected for weld quality, structural accuracy, and coating performance. Pressure and sealing tests are performed to confirm oil tightness before oil filling. All progress test results are documented and reviewed to ensure traceability, early deviation detection, and consistent manufacturing quality before final acceptance testing.
Design Tests
All transformers will be tested after finishing the production test items as follows:
♦ Leak testing with pressure for liquid-immersed transformers
♦ Test of transformer oil
♦ Measurement of voltage ratio and check of phase displacement
♦ Measurement of winding DC resistance
♦ Measurement of d. c. Insulation resistance between each winding to earth, and check of the core and frame insulation
♦ Capacitive bushing test
♦ Measurement of dissipation factor (tan δ) of the insulation system capacitances, and determination of capacitances windings-to-earth
♦ Measurement of no-load loss and current at 90%,100%,110% of rated voltage
♦ Operation test on on-load tap-changer
♦ Measurement of short-circuit impedance and load loss
♦ Lightning impulse test
♦ Induced-voltage test with partial discharge measurement
♦ Auxiliary wiring check
♦ Current transformer test
♦ Frequency response analysis test
Transformer Factory Acceptance Test
The Factory Acceptance Test (FAT) for the 158kV 250MVA Substation Autotransformer is carried out after complete assembly to verify compliance with contractual requirements and applicable standards. Routine electrical tests include winding resistance measurement, voltage ratio accuracy verification, polarity checks, and insulation resistance evaluation. Dielectric testing involves applied voltage and induced overvoltage withstand tests to confirm insulation robustness.
Performance tests assess no-load losses, load losses, impedance characteristics, and temperature rise to validate efficiency and thermal stability. Partial discharge testing evaluates insulation condition, while impulse testing verifies resistance to transient overvoltage events. Mechanical inspections include tank pressure testing, oil leakage inspection, cooling system operation checks, and tap changer functionality verification. Oil samples are analyzed to confirm dielectric strength and cleanliness. FAT results are documented in a comprehensive report and approved prior to shipment.
Routine Test - Leak Test
Voltage source (usually 500V, 1 KV or 2.5 KV, customized according to test requirements)
Temperature and humidity meter
Ground electrode
Properly connect the test equipment (such as a leak detector) to the pipe, container or sealing structure of the device under test.
Apply Test Voltage:
Apply the appropriate test pressure (e.g. 10 bar, 15 bar, etc.) depending on the equipment's operating pressure or test standard.
Applied test pressure
Leakage (can be monitored by flow meter or other equipment)
Time record (to ensure that the test time meets the standard requirements)
Initial pressure and final pressure (if any changes)
Minor leakage (good): Very small leakage is allowed, and it is necessary to judge whether it is qualified according to industry standards.
Application
Technical Advantages
Product Packaging
Related Products
FAQ From Customers
-
What is a Transformer?A transformer is an electrical device used to change the voltage of alternating current (AC). It works on the principle of electromagnetic induction, converting high-voltage current into low-voltage current or low-voltage current into high-voltage current. Transformers are widely used in power transmission, distribution systems, and various electronic devices.
-
What are the main uses of a transformer?The main use of a transformer is voltage conversion. Transformers are used in power transmission systems to help transfer electricity from power plants to consumers. In addition, transformers are also used in electronic devices such as chargers, televisions, power adapters, etc., to adjust the voltage to meet the requirements of different devices.
-
Do you have UL listed?Yes, our transformer has UL listed. We have exported to America many pad mounted transformer,substation transformer and HV.